2% slope and levelling layout have me confused

noleaf

Garden lurker
Joined
Jan 29, 2025
Messages
1
Reaction score
0
Points
1
Hi everyone. I'm undertaking a flagstone paver project. I've already got the gravel and sand I ordered to put after digging out, but I'm confused as to what the best way to leveling is to get that 2% slope. Any advice would be much appreciated
 

Attachments

  • Screenshot_20250129-194124.png
    Screenshot_20250129-194124.png
    734.3 KB · Views: 14

Rhodie Ranch

Garden Master
Joined
Nov 19, 2009
Messages
3,618
Reaction score
6,093
Points
333
Location
Southern Washington State, 8b
2% slope is about 0.12" per foot. So that would be 1.2" decline in a 10' downhill distance.

When we want slope on any surface, we add more sand and gravel to the head (start) of the project and then gradually go out thinner as we move out from the start/head.

For drainage, you've got built in drainage simply due to the sand and gravel base. A slope will insure that there will not be pooling at the head of the pavers. Unless it absolutely pours, then that will take time to percolate.
 